5TPH Rock Chrome Processing Plant In Albania

This is a rock chrome ore processing plant in Albania. JXSC adopts advanced technology and equipment to build a modern chrome ore beneficiation plant. It is equipped with feeding, coarse crushing, fine crushing, screening, ball milling and gravity separation equipment to separate the chrome concentrate. We always adhere to environmental harmony, resource conservation and rational utilization, and strive to achieve efficient development and utilization of ore.

Location

Albania, Europe

Material

Rock Chrome Ore

Capacity

5TPH

Feed Size

Around 200mm

The whole production line runs smoothly, and the complete chrome ore equipment has its use, and there is no unnecessary waste of money. I am very satisfied with no problems or equipment failures during the beneficiation process.
customer
Borsak
Senior Manager

The client’s chrome ore resources are low grade and the raw ore particles are large, so they require high-grade chrome ore. And under the premise of ensuring the construction quality of the dressing plant, the investment should be saved as much as possible.

The technological process and machinery suitable for the ore properties are recommended to develop chrome ore resources with economical rationality and reliable technology. Combined with clients needs and the actual situation on site, JXSC decided to use gravity separation process equipment to separate minerals.

The operation of the whole dressing plant is stable, the quality of the equipment is reliable, and the mineral processing indicators and economic benefits have reached expectations. The professional processing plant service strength has also been strongly affirmed and recognized by the customers of this project.

Solutions & Process

Rock Chrome Ore Processing Plant

01

Feeding

The raw ore is sent to the coarse jaw crusher by the vibrating feeder. The vibrating feeder has a sieve bar, and the coarse grain on the sieve is sent to the coarse jaw crusher. The fine aggregates under the sieve are sent to the cone crusher for fine crushing through the conveyor.

02

Crushing

The cone crusher breaks the rock chromium down to less than 20 mm. + 20 mm of material is sent back to the cone crusher for crushing again. The 0-20mm materials under the sieve are transported to the storage bin.

03

Grinding

The 0-20mm powder is smoothly fed into the ball mill through the electromagnetic vibrating feeder and belt conveyor and used in conjunction with the spiral classifier. The oversized particles from the classifier are returned to the ball mill for grinding again to form a closed loop mill to obtain materials below 200 mesh.

04

Separation

The less than 200mesh materials will be pumped into the spiral chute and shaking tables. To maximize chrome ore recovery, we adopts secondary spiral chute separation. The middle material of the first-stage spiral chute is pumped to the second-stage spiral chutes group, and the discharged concentrate enters the shaking table together to obtain high-grade chrome concentrate.